1. Develop a budget for the project described in Table 11.11 assuming that the cost of each activity is linearly distributed over its duration.

and

2. Assume an early-start schedule.

b. Assume a late-start schedule.

c. Assume that a leveled budget is desired (i.e., the same daily cost is desired for each day of the project).